67036f45b0 Scheduler-test: Integration-test now running smoothly
The last round of refactorings yielded significant improvements
 - parallelisation now works as expected
 - processing progresses closer to the schedule
 - run time was reduced

The processing load for this test is tuned in a way to overload the
scheduler massively at the end -- the result must be correct non the less.

There was one notable glitch with an assertion failure from the memory manager.
Hopefully I can reproduce this by pressing and overloading the Scheduler more...
2023-12-18 23:34:10 +01:00
347b9b24be Scheduler-test: complete and integrate computational load
This basically completes the Chain-Load framework;
a simple Scheduler integration run with all relevant features
can now be demonstrated.
2023-12-11 19:42:23 +01:00
7eca3ffe42 Scheduler-test: a helper for one-time operations
Invent a special JobFunctor...
 - can be created / bound from a λ
 - self-manages its storage on the heap
 - can be invoked once, then discards itself

Intention is to pass such one-time actions to the Scheduler
to cause some ad-hoc transitions tied to curren circumstances;
a notable example will be the callback after load-test completion.
2023-12-08 03:16:57 +01:00
c8f13ca3e6 Chain-Load: initial draft
...design a pattern to generate a reproducible computation load
2023-11-11 01:05:54 +01:00
3135887914 Scheduler: connect BlockFlow capacity announcement
...refine the handling of FrameRates close to the definition bounds
...implement the actual rule to scale allocator capacity on announcement
...hook up into the seedCalcStream() with a default of +25FPS

+ test coverage
2023-11-10 23:52:20 +01:00
b61ca94ee5 Scheduler: rectify λ-post API
...to bring it more in line with all the other calls dealing with Activity*
...allows also to harmonise the ActivityLang::dispatchChain()
...and to compose the calls in Scheduler directly

NOTE: there is a twist: our string-formatting helper did not render
custom string conversions for objects passed as pointer. This was a
long standing problem, caused by ambiguous templates overloads;
now I've attempted to solve it one level more down, in util::StringConv.
This solution may turn out brittle, since we need to exclude any direct
string conversion, most notably the ones for C-Strings (const char*)

In case this solution turns out unsustainable, please feel free
to revert this API change, and return to passing Activity& in λ-post,
because in the end this is cosmetics.
2023-10-23 01:48:46 +02:00
e5638119f5 Scheduler: devise scheme for load control
- organise by principles rather than implementing a mechanism
- keep the first version simple yet flexible
- conduct empiric research under synthetic load

Basic scheme:
- tend for next
- classify free capacity
- scattered targeted wait
2023-10-22 16:45:13 +02:00
74c97614b3 Scheduler: component wiring
The »Scheduler Service« will be assembled
from the components developed during the last months
- Layer-1
- Layer-2
- Activity-Language
- Block-Flow
- Work-Force
2023-10-20 04:36:07 +02:00
9ce3ad3d72 Scheduler: Layer-2 complete and tested (see #1326)
* the implementation logic of the Scheduler is essentially complete now
 * all functionality necessary for the worker-function has been demonstrated

As next step, the »Scheduler Service« can be assembled from the two
Implementation Layers, the Activity-Language and the `BlockFlow` allocator
This should then be verified by a multi-threaded integration test...
2023-10-19 01:49:08 +02:00
0431a14584 Scheduler: Layer-1 complete and tested 2023-10-17 04:35:58 +02:00
997fc36c81 Workforce: implementation complete 2023-09-09 23:42:13 +02:00
70cd8af806 Workforce: requirement analysis 2023-09-05 00:22:17 +02:00
2e28f5d278 Activity-Lang: abstracted execution framework complete and tested (closes: #1319) 2023-09-03 01:50:50 +02:00
180c6b8d84 Block-Flow: define next steps to construct
...continue to proceed test-driven
...scheduler internals turn out to be intricate and cohesive,
   and thus the only hope is to adhere to strict testing discipline
2023-07-13 01:51:21 +02:00
23a6fbdf4f Scheduler: investigate modes of operation
- analysis of Activity usage
- derive possible memory management schemes
- research regarding asynchronous IO
- decision regarding the memory management scheme
2023-07-03 18:40:37 +02:00