LUMIERA.clone/doc/devel/rfc/SchedulerRequirements.txt
Ichthyostega c7528bbe8a clean-up: some RfCs became effectively final
The purpose of RfCs is to channel and document discussions
among a group of developers regarding questions of design.
While there is unfortunately no longer a group of developers
discussing matters and working together on the code base,
some questions can be considered more or less settled,
by being implemented and validated.

- the Scheduler
- structure of the Developer Documentation
- Application installation as relocatable bundle
2025-09-21 05:40:15 +02:00

221 lines
9.8 KiB
Text

SchedulerRequirements
=====================
// please don't remove the //word: comments
[options="autowidth"]
|====================================
|*State* | _Final_
|*Date* | _Mi 09 Jan 2013 12:04:03 CET_
|*Proposed by* | Ichthyostega <prg@ichthyostega.de>
|====================================
********************************************************************************
.Abstract
Define the expected core properties and requirements of the Scheduler service.
********************************************************************************
The rendering and playback subsystem relies on a *Scheduler* component to invoke
individual frame rendering and resource fetching jobs. This RfC summarises the
general assumptions and requirements other parts of the application are relying
on
Description
-----------
//description: add a detailed description:
The *Scheduler* is responsible for getting the individual _render jobs_ to run.
The basic idea is that individual render jobs _should never block_ -- and thus
the calculation of a single frame might be split into several atomic jobs,
including resource fetching. This expected usage should be considered together
with the data exchange protocol defined for data output through the `OutputSlot`
instances; moreover the extended data of the low-level model can be hot-swapped
while rendering continues to go on, necessitating to release blocks of superseded
model data at well defined points. Combining all these known usage constraints
leads to the following requirements for the scheduler:
ordering of jobs::
the scheduler has to ensure all prerequisites of a given job are met
job time window::
when it is not possible to run a job within the defined target time window, it
must not be run any more but rather be marked as failure
failure propagation::
when a job fails, either due to an job internal error, or by timing glitch,
the effect of this failure needs to propagate reliably; we need a mechanism
for dependent jobs to receive a notification of such a failure state
conditional scheduling::
we need to provide some way to tie the activity of jobs to external conditions,
notable examples being the availability of cached data, or the arrival of data
loaded from storage
superseding of planned jobs::
changes in playback modes require us to ``change the plan on-the-fly'' --
essentially this means we need to 'supersede' a group of already planned jobs.
Moreover, we need certain ordering guarantees to ensure the resulting switch
in the effective output data happens once and without glitches.
The scheduler interface and specification establishes some kind of micro-language
to encode the patterns of behaviour prompted by the playback control and the
interpretation of the render node model. Together these basic requirements
help to address some relevant themes
dependency on prerequisites
~~~~~~~~~~~~~~~~~~~~~~~~~~~
Render tasks don't exist in isolation; they depend on prerequisites, both preceding
calculations and the availability of data. Since our primary decision is to avoid
blocking waits, these prerequisites need to be modelled as other jobs, which leads
to dependencies and conditional scheduling.
detecting termination
~~~~~~~~~~~~~~~~~~~~~
The way other parts of the system are built, requires us to obtain a guaranteed
knowledge of some specific job's termination. More precisely, we need to find out
when a ``stream of calculations'' has left a well defined domain -- and this can
be modelled by the activation of specific marker jobs. It is possible to obtain
that knowledge with some timing leeway, but in the end, this information needs
to arrive with absolutely reliability (memory management will rely on them,
and thus failure might lead to out-of.memory or segfault).
job scheduling modes
~~~~~~~~~~~~~~~~~~~~
The scheduler offers various modes of treatment on a per job base. The default is to
handle jobs as _time-bound_, with a moderate latency. Alternatively jobs can be handled as
_background_ jobs, as _freewheeling_ jobs (maximum usage of performance and bandwidth),
or as _low-latency timed_ jobs.
latency, reliability and precision
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
By involving a scheduler component we employ an asynchronous calculation model.
This allows and necessitates to define special guarantees regarding various properties
of job execution.
- it is acknowledged that every scheduling involves some *latency* -- which needs to be
included into any calculation of deadlines. The latency limits the minimum time window
we can target for scheduling an operation
- it is acknowledged that timing specifications include some degree of fuzziness -- but
it is possible to give guarantees regarding correctness. The defined state transitions
and notifications will happen *reliably*
- it is acknowledged that the behaviour of the scheduler is non-deterministic (the way
this term is used in computer science). Yet still we'll impose some ordering guarantees,
which will be observed with *precision*: both the _adding_ and the _superseding_ of
a group of jobs happens in a transactional way, to retain the ordering according
to dependency and job time.
Tasks
~~~~~
// List what needs to be done to implement this Proposal:
// * first step [yellow-background]#WIP#
* define the job interface ([green]#✔ done#)
* define a protocol for job state handling ([green]#✔ done#)
* define the representation of dependencies and the notifications in practice ([green]#✔#)
* verify the proposed requirements by an scheduler implementation sketch ([green]#✔#)
Discussion
~~~~~~~~~~
Pros
^^^^
// add a fact list/enumeration which make this suitable:
* the entity ``job with defined properties'' serves as an interface
* open and complex patterns of behaviour can be built on top
* a proper scheduler replaces several other mechanisms (threaded output backend, producer-consumer queue
with locking, GUI animation services)
* to provide an _atomic execution service_ allows us to control various aspects of execution explicitly
* in the end, this enables to scale and use various kinds of hardware
Cons
^^^^
// fact list of the known/considered bad implications:
* there is no ``while-loop'' to base any playback control structures on
* compliance to externally imposed deadlines and memory management are challenging.
Alternatives
^^^^^^^^^^^^
//alternatives: explain alternatives and tell why they are not viable:
. use a synchronous player with buffering
. use a simplistic scheduler with entirely atomic jobs
We do not want (1), since it is tied to an obsolete hardware model and lacks the ability to be
adapted to the new kinds of hardware available today or to be expected in near future. We do not
want (2) since it essentially doesn't solve any problem, but rather pushes complexity into the higher
layers (Session, Stage), which however are lacking information about individual jobs and timing.
Rationale
---------
//rationale: Give a concise summary why it should be done *this* way:
We use a scheduler to gain flexibility in controlling various aspects of computation and I/O usage.
Moreover, we turn the scheduler into an interface between the Vault and Steam-Layer; while the exact
outfitting of the individual jobs highly depends on internals of the Session and Engine models,
the properties of _actual job execution_, closely related to system programming, are linked
to the Vault. The actual requirements outlined in this RfC are derived from the internals
of the player implementation, while _the way_ these requirements are defined, and especially
the aspects _omitted_ from specification are derived from knowledge regarding the possible
scheduler and vault layer implementation.
Conclusion
----------
//conclusion: When approved (this proposal becomes a Final)
// write some conclusions about its process:
A solution closely following this proposal was implemented and became a
centrepiece of the Lumiera Render Engine. There was no further formal
decision, since _Ichthyo_ worked alone during the past years.
Comments
--------
//comments: append below
.State -> Draft
This RfC emerged from the work on the _player implementation_, which is the immediate
client built on top of the scheduler service. At FrOSCon 2013 and the following developer meeting,
we had an extended discussion covering various aspects of the possible scheduler implementation.
The goal is to settle down on an interface definition, so the player and engine implementation
can be developed independently of the scheduler implementation
Ichthyostega:: 'Do 19 Sep 2013 21:31:07 CEST' ~<prg@ichthyostega.de>~
.State -> Final
After an extended intermission, where development was focused at GUI topics, the integration
work since 2023 strives at achieving an initial integration of the Render Engine. As part of the
https://issues.lumiera.org/ticket/1221[#1221 »PlaybackVerticalSlice«], an implementation of the
Scheduler, as proposed by this RfC, was
link:/x/imp/Scheduler.html[built from scratch and tested extensively]. Practical experience
during this effort leads to the following refinements:
- the Scheduler does not invoke Jobs, +
but processes _verbs_ from an _Activity Language_ rather.
- this language in turn embodies a primitive to check a dependency count
- an external event may re-trigger such a chain of Activities within the Scheduler
- an extent-based memory manager can be based on deadlines of these Activities.
- the Scheduler becomes a passive management task, pulled by a active Workers.
- Workers manage their capacity through a statistical distribution of _sleep times._
In this form, the proposal can be considered as implemented. +
^(see -> https://git.lumiera.org/?p=LUMIERA;a=commit;h=d71eb37[d71eb37]
and https://issues.lumiera.org/ticket/1344[#1344])^
Ichthyostega:: '2024-04-20 01:55 CEST'